EVA塑料止水帶的施工方法及注意事項
Construction methods and points for attention of EVA plastic water stop belt
EVA塑料止水帶它由PVC聚氯乙烯樹脂及各種填加劑,經混合、造粒、擠出等工序而制成的止水材料。此產品利用彈性體材料具有的彈性變形特性在建筑構造接縫中起到防漏、防滲作用,并且具有耐腐蝕、耐久性好的特點。
EVA plastic water stop belt, it is made of PVC polyvinyl chloride resin and various filling agent, through mixing, granulation, extrusion and other processes made of water sealing material. This product utilizes the elastic deformation property of elastomer materials to prevent leakage and prevent seepage in the structural joints of the building, and has the characteristics of corrosion resistance and good durability.
@赤峰EVA300*6塑料止水帶

EVA塑料止水帶主要用于混凝土澆注時設置在施工縫及變形縫內與混凝土構成為一體的基礎工程。如隧道、涵洞、引水渡槽、攔水壩、貯液構筑物、地下設施等。PVC塑料止水帶施工方法與普通的橡膠止水帶相同。在澆埋時要使其與混凝土界面貼合平整,接頭部分粘接緊固,澆埋過程中要以適當的力充分震搗混凝土,使其與混凝土結合良好,以獲得最佳的止水效果。PVC塑料止水帶施工注意中要注意一些問題,由于混凝土中有許多尖角的石子和鋼筋,操作是要注意避免對止水帶造成機械損傷。在定位塑料止水帶時,要使其與混凝土界面貼合平整,不能出現止水帶翻轉、扭曲等現象,否則應及時進行調正在澆筑固定止水帶時,應防止止水帶發生偏移,影響止水效果。此種塑料止水帶接頭可利用粘接、熱焊接等方法,保證接頭牢固。澆注混凝土過程中要注意充分震搗,以達到止水帶和混凝土充分結合。
EVA plastic water stop belt is mainly used for concrete pouring, it is installed in the construction joints and deformation joints, and concrete as one of the basic works. Such as tunnel, culvert, aqueduct, dam, reservoir structures, underground facilities, etc.. The construction method of PVC plastic water stop belt is the same as that of ordinary rubber water stop belt. In the pouring buried to make it smooth and fit the concrete interface, the joint part of the adhesive fastening, pouring process to buried in an appropriate capacity of fully vibrating concrete, the good combination with concrete, in order to obtain the best sealing effect. PVC plastic water stop construction should pay attention to some problems, because there are many pointed stones and steel reinforcement in the concrete, the operation should pay attention to avoid mechanical damage to the water stop belt. In the positioning of the plastic waterstop, to make it smooth and fit the concrete interface, can not appear waterstop flip, twist phenomenon, otherwise should be timely adjusted is pouring fixed sealing strip, should prevent the waterstop shift, affecting sealing effect. The joint of the plastic water stop belt can be firmly secured by bonding and heat welding. In the process of pouring concrete, attention should be paid to the full shock and tamping so as to achieve the full combination of the water stopping belt and the concrete.
EVA塑料止水帶施工方法與橡膠止水帶相同。在澆埋時要使其與混凝土界面貼合平整,接頭部分粘接緊固,澆埋過程中要以適當的力充分震搗混凝土,使其與混凝土結合良好,以獲得最佳的止水效果。
@赤峰EVA300*6塑料止水帶

EVA plastic stop belt construction method is the same as rubber water stop belt. In the pouring buried to make it smooth and fit the concrete interface, the joint part of the adhesive fastening, pouring process to buried in an appropriate capacity of fully vibrating concrete, the good combination with concrete, in order to obtain the best sealing effect.
A.在施工過程中,由于混凝土中有許多尖角的石子和鋼筋,操作是要注意避免對塑料止水帶造成機械損傷。
A. in the course of construction, because there are many pointed stones and reinforcing bars in the concrete, the operation should pay attention to avoid the mechanical damage to the plastic water stopping belt.
B.在定位塑料止水帶時,要使其與混凝土界面貼合平整,不能出現止水帶翻轉、扭曲等現象,否則應及時進行調正。
B. in the positioning of plastic water stop, to make it and the concrete interface leveling, can not appear "water stop", "flip", "distortion" and so on, otherwise should be timely adjustment.
C.在澆筑固定止水帶時,應防止止水帶發生偏移,影響止水效果。
When C. is pouring the fixed water stop belt, it should prevent the water stop belt from deviation and influence the water stopping effect.
D.止水帶接頭可利用粘接、熱焊接等方法,保證接頭牢固。 E.澆注混凝土過程中要注意充分震搗,以達到止水帶和混凝土充分結合。
D. joint of water stop belt can be secured by bonding and thermal welding. In the process of pouring concrete, E. should pay attention to the full vibration to achieve the full combination of the water stopping belt and concrete.